• We are expecting some steel beams to be delivered sometime tomorrow or Tuesday (9.27). This could cause a bit of street blockage while they are dropped off and moved on site. We'll make sure they're quick.
• A cement pour, for now, is scheduled for Wednesday. We will be pouring the garage slab as well as another slab elsewhere in the house. This will involve two trucks at most, should take roughly 1/2 a day and will begin first thing in the morning.
We're definitely progressing!!