An "all in one" post to cover the changes in plans:
1) The drilling of the piers will now, we are told, begin tomorrow (Thursday) morning. This will involve another larger excavator being dropped off to perform the work. Undoubtedly this will block the street for several minutes as it is unloaded and cause a considerable amount of noise for the next few days as the piers are drilled.
2) The pier cages themsevles - 40 or so 15ft rebar circular cages - will be dropped off either tomorrow (Thursday) or Friday and will be stored off the street on the 5 Dos Posos driveway. As with any large delivery, there could be some time where the street is blocked - at least partially.
3) The trash pick-up should occur on the same day that the excavator for the drilling is dropped off - hopefully that will be tomorrow.
Thanks for your patience. Always hard to keep schedules from changing but we're doing our best to keep things under control.