Monday, July 6, 2009

Form Building Continues

The foundation form building will continue this week, which will include the delivery and arrival of rebar with a rebar crew to install it - this will undoubtedly include a truck that will be parked at the top of the driveway. We will be sure to allow enough room for cars to pass. This will most likely occur Tuesday or Wednesday and will take probably one or two days in total.

Also, early in the week (hard to tell despite our efforts), we will have PG&E here to trench up our gas line and cap it at the street for the remainder of the project.

The cement pour for the forms will probably be early next week - we'll keep you posted.

Thanks, as always, for your patience as we move forward.